Key takeaways
- Production planning and control has two halves. Planning decides what to make, on which machine and when. Control keeps the plan true through dispatching, expediting, inspection and corrective action.
- A weekly loop works for a 20 to 200 person plant: order book, material check, capacity check by machine, schedule, daily review.
- MPS says what finished goods to make and when. MRP works backwards from it to the materials and parts needed.
- Most plans fail on three things: urgent orders jumping the queue, material not checked, and no feedback from the floor.
Production planning and control (PPC) is how a factory decides what to make, where and when, and then keeps the floor on that plan. This guide is for the planner who must make Monday’s plan survive until Saturday, in a 20 to 200 person plant.
What is production planning and control, and what is the PPC process?
Production planning and control is the function that decides what to produce, in what quantity, on which machine and by which date, then monitors the floor and corrects deviations. Planning covers forecasting, routing, loading and scheduling. Control covers dispatching, expediting, inspection and corrective action.
The PPC process runs as a loop, not a straight line. You plan from orders and stock, release work to the floor, watch what actually happens, and feed the gap back into next week’s plan. In a small plant one person may do it all, often the owner or a senior supervisor. In a larger plant, a PPC department sits between sales, stores, production and purchase. Its output is simple: a schedule that production believes, stores can supply and sales can quote from. If the floor ignores the schedule, you do not have planning, you have a document.
What are the steps of production planning?
The steps of production planning are: forecast or collect orders, prepare the route for each part, check material and capacity, load machines, schedule jobs, release work orders, then follow up. Different books count five or seven steps, but the sequence is the same.
Forecasting or order intake: confirmed orders for a make-to-order plant, a forecast for make-to-stock. Routing: the sequence of operations and machines for each part, with standard times. Loading: assigning hours to each machine and checking they fit the week. Scheduling: setting start and finish times by job, usually backwards from the due date. Dispatching: releasing the job card, drawing and material to the floor. Follow-up or expediting: chasing late material and jobs. Inspection and corrective action: catching problems at the stage they happen, then fixing the cause. A job card is the document that carries the plan to the machine and brings the actuals back.
Make-to-order or make-to-stock: how does it change planning?
A make-to-order job shop plans against firm customer orders and due dates, so its main risk is capacity and material for each job. A make-to-stock plant plans against a forecast, so its main risk is building the wrong quantity. The tools are the same, but the questions differ.
A CNC or fabrication shop with many part families is a job shop: each order has its own drawing, route and date. Planning here is mostly loading and sequencing, and the key question is ‘can we promise this date?’. A packaged-goods or standard-component plant builds stock against expected demand. There the key question is ‘how much, and when do we top up?’. Many Indian plants are mixed: a few fast-moving items made to a stock level, the rest made to order. Plan the two separately. Give stock items a reorder level and a standard batch, and give order items a promise-date check against machine load. Mixing them in one list is how a repeat item runs out while a one-off job takes the machine.
What does a weekly planning loop look like in a 20 to 200 person plant?
A good weekly loop has five steps: review the order book, check material, check capacity machine by machine, publish the schedule, and hold a short daily review. Run it the same day each week, with the same people. Consistency matters more than sophistication.
Friday afternoon or Monday morning: sales, production, stores and quality sit for 30 minutes. First, the order book: which orders are due this week and next, and which are new? Second, material: for each job, is raw material, bought-out parts and tooling in stock or on its way, with a date? A job with no material is not ready, so leave it off the schedule. Third, capacity: for each machine, how many hours are available after planned maintenance and holidays, and how many are loaded? Fourth, the schedule: put jobs in sequence by due date and changeover similarity, and print it for each supervisor. Fifth, the daily review: 10 minutes each morning to check what was planned against what happened, and what is now late. Track work in progress (WIP) at each stage so you can see where jobs wait. See ERP for manufacturing for what software can take over once the loop works on paper.
What is the difference between MRP and MPS?
MPS (Master Production Schedule) states which finished products to make, how many, and by when. MRP (Material Requirements Planning) takes the MPS and the bill of material, subtracts stock on hand and orders, and calculates which materials and parts to buy or make, and when. MPS is the what; MRP is the how.
Take an example: you commit to 200 pump assemblies in the second week. That is the MPS. Each assembly needs a casting, a shaft, a seal and eight bolts. MRP multiplies out the bill of material, nets against stock and open purchase orders, and tells you to order, say, castings by a date that allows for the supplier’s lead time. In a small plant, you can do MRP in a sheet with one line per material: need, stock, on order, short. It does not require a system. It requires accurate bills of material and honest stock numbers, which is where most plants struggle. The MRP overview explains the logic in more detail.
Why do production plans fail on the floor?
Plans fail for three reasons: urgent orders jump the queue and wreck the sequence, material is not checked before release, and the floor gives no feedback. Each is a process gap, not a people problem, and each can be fixed with a simple rule.
Urgent orders: when the owner or sales calls and pushes a job to the front, every other job slips and nobody tells those customers. Fix: a rule that an urgent job is allowed, but the planner must say which job it displaces and by how much, and it is written down. Material not checked: a job released without raw material blocks the machine and the operator, then moves to something else, and now two jobs are half done. Fix: no release without a material tick. No feedback: supervisors do not report what was actually produced, so next week’s plan rests on guesswork. Fix: one number per job per shift, written on the job card and collected each morning. Add to these a fourth failure: planning each department’s tasks without looking at the bottleneck machine. Load the bottleneck first and everything else follows it.
A plan nobody checks against the floor is a wish. The real planning happens at 9 a.m., when you compare yesterday’s numbers with the schedule and decide what to move.— Murtaza Udaypurwala, DESENO
Which production planning software or tool should you use?
Climb a ladder: whiteboard, Excel, Tally plus a sheet, then PPC or MES software. Move up only when the lower step breaks, for example when jobs exceed what a board can show or the sheet is edited by too many hands. Production planning software works only on top of a plan the team already trusts.
The table maps each PPC stage to the question it answers and the simplest tool that works.
| PPC stage | Question it answers | Simplest tool |
|---|---|---|
| Order intake | What is due this week and next? | Order book sheet or whiteboard |
| Routing | Which operations, which machines, how long? | Route sheet per part |
| Material check | Can we start this job? | Stock list from Tally plus a tick column |
| Loading | Will this fit machine hours this week? | Excel load chart by machine |
| Scheduling | What runs first, and when is it done? | Printed schedule or board |
| Dispatching | Does the floor have the card, drawing and material? | Job card at the machine |
| Follow-up and control | What is late, and why? | Daily 10-minute review plus WIP sheet |
The bottom line
Production planning and control is a weekly habit, not a software purchase. Check material before release, load the bottleneck machine first, protect the sequence from urgent jobs and collect one number per job per shift. Software helps once that habit exists.
If you want dashboards and alerts on top of your current sheets and Tally exports, our software and automation work builds them around how your planner already works.
Frequently asked questions
What is production planning and control?
Production planning and control is the function that decides what to make, how much, on which machine and by when, then tracks the floor and corrects problems. Planning covers forecasting, routing, loading and scheduling. Control covers dispatching, expediting, inspection and corrective action.
What are the 5 steps of production planning?
A common five-step version is: collect orders or forecast demand, prepare routing, check material and capacity, schedule jobs on machines, and release and follow up. Some books split these into seven steps, but the order stays the same and the loop repeats weekly.
What is the process of PPC?
The PPC process is a loop. You gather orders, plan routes and capacity, schedule jobs, release them to the floor, monitor what actually happens through job cards and daily reviews, and feed delays and rejections back into the next plan. It never ends, it just repeats.
What is the difference between MRP and MPS?
MPS is the master production schedule: which finished products to make, how many and by when. MRP takes that schedule and the bill of material, subtracts stock and open orders, and calculates what materials and parts must be bought or made, and when.
Do small factories need production planning software?
Not at first. A whiteboard or Excel sheet with a material-ready column and a load chart by machine is enough for many plants of 20 to 50 people. Software helps when job volume, edit conflicts or reporting needs outgrow the sheet, and only on top of a plan that works.
What is a production schedule template?
A production schedule template is a sheet that lists jobs in sequence with part, quantity, machine, planned start and finish, material status and due date. Add actual start and finish columns so the schedule becomes a control tool, not just a plan.